Quick answer ACM panels are installed by fabricating each panel into a tray, then fixing it to a subframe of girts or rails over the weather barrier, using one of four main systems: wet-seal, dry route-and-return, rainscreen or cassette. Whatever the system, the panels must be free to expand and contract, every joint must manage water, and the full wall assembly must match the tested design where NFPA 285 applies. |
Most problems people blame on ACM panels, such as waves in the face, leaks at joints and stained sealant, have very little to do with the panel itself. They come from how the panels were fabricated and fixed to the building.
This guide walks through how ACM is installed on US commercial buildings: the main systems, the framing behind them, the joint and fastener details that matter, and the mistakes that cause call-backs. It is written for general contractors, architects and owners who want to understand what a good installation looks like before the crew shows up.
The parts of an ACM wall
A modern ACM facade is a layered system. From the inside out, a typical wall looks like this:
• Backup wall: steel studs with sheathing, concrete or masonry.
• Weather-resistive barrier (WRB): a membrane that keeps water out of the backup wall.
• Continuous insulation: mineral wool or foam boards, depending on the fire strategy.
• Subframe: aluminum or galvanized steel girts, Z-channels or rails that create a cavity and carry the panels.
• Panel attachment: clips, extrusions or fasteners that hold the panels to the subframe.
• ACM panels: routed and folded aluminum composite panels, usually 4 mm thick.
Because ACM is part of this assembly, any change to the insulation or WRB can affect fire performance. On buildings where NFPA 285 applies, the whole stack has to match a tested assembly.
Step one: fabrication
ACM is rarely hung as a flat sheet. Each panel is turned into a shallow tray, either in a shop or on site.
• Routing: a V or U groove is cut into the back face, through the inner skin and most of the core, leaving the outer skin and a thin layer of core.
• Folding: the edges are bent up along the groove to form returns, usually 1 to 2 inches deep.
• Corners: the corners are notched and joined with corner clips or rivets.
• Extrusions: perimeter extrusions or stiffeners are attached, depending on the system.
Fold slowly and in one motion. Re-bending a routed edge cracks the outer skin. Viva's guide to ACP fabrication and fitting shows the routing and folding steps in detail.
The four main installation systems
|
System |
How it works |
Strengths |
Watch-outs |
|
Wet-seal (clip and caulk) |
Trays fixed with clips; joints filled with backer rod and silicone sealant |
Lowest cost, fast, tolerant of site conditions |
Relies on sealant; needs regular joint inspection |
|
Dry route-and-return |
Trays hung on extrusions with open or gasketed joints |
Clean shadow lines, less sealant to maintain |
Needs careful flashing and WRB detailing behind open joints |
|
Rainscreen (pressure-equalized) |
Open joints with a ventilated, drained cavity behind |
Best water management, especially in wet or windy climates |
More components and design effort |
|
Cassette or hook-on |
Shop-made cassettes hang on pins or hooks on the subframe |
Crisp detailing, easy panel replacement, fast on site |
Highest cost, less flexible for field changes |
For buildings in the Pacific Northwest, the Gulf Coast or anywhere with heavy wind-driven rain, a rainscreen approach is worth the extra cost. Viva's rainscreen system is built for exactly this job.
Framing and the subframe
The subframe is where a lot of the real engineering happens.
• Design girts and clips for the wind loads in your local code, including higher corner and edge zones.
• Use thermally broken clips where energy codes push for lower heat loss through the wall.
• Keep the subframe straight and true. ACM shows every wave in the framing behind it.
• Use aluminum or properly galvanized steel, and separate dissimilar metals to prevent galvanic corrosion.
• Leave a drained, ventilated cavity behind the panels on rainscreen systems.
Thermal movement: the detail that makes or breaks it
Aluminum expands about 0.013 thousandths of an inch per inch for every degree Fahrenheit. In plain terms, a 10 foot panel can grow by roughly 1/8 to 3/16 inch between a cold winter night and a hot summer afternoon, and dark colors in full sun move the most.
• Fix each panel at one point and let the others slide in slotted holes or on clips.
• Never over-tighten fasteners. They should hold the panel without clamping it.
• Set joint widths to allow for movement, typically around 1/2 inch for many route-and-return systems.
• Add stiffeners on large panels to reduce bowing and oil-canning.
Most waviness people notice on ACM facades in hot afternoons comes from panels that were locked in place and have nowhere to move.
Joints, sealants and water management
|
Joint type |
Used in |
Key detail |
|
Sealed joint |
Wet-seal systems |
Backer rod plus a compatible silicone; tool the bead and check adhesion |
|
Open joint |
Rainscreen systems |
A continuous, UV-resistant WRB behind, with drained cavities |
|
Gasketed joint |
Some dry systems |
Gaskets must be continuous and correctly lapped at intersections |
|
Reveal or channel joint |
Dry systems |
Extrusions or channels sized to drain water down and out |
Pay special attention to windows, parapets, soffits and transitions to other materials. Most leaks start at these interfaces, not in the field of the wall.
Fasteners and hardware
• Use stainless steel or coated fasteners rated for exterior use and for contact with aluminum.
• Drill oversized or slotted holes in the panel for floating fixings.
• Use rivets with the right grip range; loose rivets rattle and over-tight ones restrain the panel.
• Isolate aluminum from steel with washers or tape where they meet.
Fire and code coordination
Under the 2021 and 2024 International Building Code, ACM on Type I to IV construction has fire limits at every height, and above 40 feet the wall assembly must pass NFPA 285. That has two direct effects on installation.
• The insulation, WRB and joint details on site must match the tested assembly, or be covered by a qualified engineering judgment.
• Substitutions during construction, even small ones, need sign-off from the design team before they are installed.
Make sure the installer has the tested assembly drawings on site, not just the panel product data.
Planning and sequencing on site
A smooth ACM installation starts well before the first panel arrives. The order of work makes a big difference to quality and schedule.
• Shop drawings first: get panel layouts, joint lines and details approved before fabrication starts.
• Field verify the building: measure openings and slab edges, because buildings are rarely built exactly to the drawings.
• Weather barrier and flashing: complete and inspect them before the subframe goes on.
• Subframe survey: check the girts for line and level; fix problems now, not after the panels are up.
• Install from the bottom up: start at the base flashing and work up, so each course sheds water over the one below.
• Protect finished work: keep finished elevations clear of welding sparks, mortar and other trades.
Climate and season considerations across the US
|
Condition |
What it affects |
What to do |
|
Hot summers (Sun Belt) |
Thermal movement, sealant curing, film baking on |
Allow for movement, remove film promptly, avoid sealing in extreme heat |
|
Cold winters (Northeast, Midwest) |
Sealant application and adhesion |
Follow sealant temperature limits; keep surfaces dry and frost free |
|
Hurricane zones (Gulf and Atlantic coasts) |
Wind loads and product approvals |
Design to local wind speeds and check state or county approvals |
|
Wet climates (Pacific Northwest) |
Water management at joints |
Favor rainscreen systems with drained, ventilated cavities |
Who is responsible for what
|
Party |
Main responsibility |
|
Architect |
Design intent, panel layout and the tested fire assembly |
|
Facade engineer or consultant |
Wind design, subframe and attachment details |
|
Panel supplier |
Panels, finishes, test data and fabrication guidance |
|
Fabricator |
Routing, folding and assembling the trays to the shop drawings |
|
Installer |
Subframe, panel installation, joints and protection of finished work |
|
General contractor |
Coordination with other trades and approval of any substitutions |
Common installation mistakes
• Locking panels rigidly so they bow in the heat.
• Uneven framing that telegraphs through the face.
• Re-bending routed edges, which cracks the outer skin.
• Leaving protective film on for months, so it bakes onto the paint.
• Mixing production batches on one elevation, which can show small color differences.
• Installing metallic panels in different directions, which makes them look like different colors.
• Swapping insulation or WRB without checking the tested fire assembly.
Inspection and handover checklist
• Panels flat and aligned, with even joint widths.
• Arrows on the protective film all pointing the same way before removal, then film fully removed.
• Sealant joints continuous, tooled and fully adhered.
• Flashings and drainage paths clear at windows, parapets and the base of the wall.
• Documentation handed over: as-built drawings, product data, tested assembly details and warranties.
Why work with Viva
Viva, which describes itself as Asia's largest ACP manufacturer, produces ACM in PE, fire-retardant and A2 cores, with PVDF finishes in over 500 shades and custom colors. It runs more than 15 production lines and 5 color coating lines, carries out more than 250 in-house quality tests, and provides installation guidelines and technical support through more than 30 global branches.
Frequently asked questions
How are ACM panels installed?
ACM panels are routed and folded into trays, then fixed to an aluminum or galvanized steel subframe over the weather barrier and insulation. The main systems are wet-seal, dry route-and-return, rainscreen and cassette. Each lets the panels move with temperature and manages water at the joints.
What is the difference between wet-seal and dry ACM systems?
Wet-seal systems fill the joints with backer rod and silicone sealant, which is cheaper but relies on the sealant over time. Dry systems use open or gasketed joints with extrusions and a well-detailed weather barrier behind, giving cleaner lines and less sealant maintenance.
What joint width do ACM panels need?
Many route-and-return systems use joints of around 1/2 inch, but the right width depends on the system, panel size and climate. Always follow the system designer and panel supplier, and make sure the joint allows for thermal movement.
Do ACM installations need NFPA 285?
Under the 2021 and 2024 IBC, ACM on Type I to IV buildings installed more than 40 feet above grade must be part of an exterior wall assembly that has passed NFPA 285. The installed insulation, barrier and joints must match that tested assembly.
When should protective film be removed from ACM panels?
Remove it as soon as practical after installation, within the time limit the panel supplier gives. Film left on for months in sun and heat can bond to the paint and become very hard to remove without damaging the finish.
Can ACM panels be installed in winter?
Yes, but sealant work needs care. Most silicone sealants have minimum application temperatures, and surfaces must be clean, dry and free of frost. Panels themselves can be installed in cold weather, with joint widths set to allow for the movement that will come in summer.
Planning an ACM facade? Send your drawings, building height and preferred system through the quote request form, and the Viva team will advise on panel grade, fabrication and installation details.
Explore the ranges
Published by VIVA - Asia's Largest Manufacturer of Aluminium Composite Panels. 15M sq.mt capacity | 500+ shades | Thomas Bell-Wright FR A2+ Certified


en
Spanish
Arabic
Swahili
French